Commercial Projects
We perform injection works on commercial and industrial facilities of various purposes — from retail and public buildings to warehouses, logistics, and production complexes. Soil injection technologies, base stabilization, lifting of concrete structures, and excavation pit protection allow us to effectively work with facilities at any stage of construction or operation.
Our solutions are used to eliminate settlement, deformations, and risks of loss of load-bearing capacity, as well as to reinforce excavation walls in complex soil conditions. Inject operates under high loads, limited access, and active infrastructure, ensuring predictable results and long-term structural stability without stopping facility operation.
-
Shopping centers, stores, supermarkets, and hypermarkets
-
Gas stations, service, and roadside complexes
-
Educational and public institutions (schools, lyceums, administrative buildings)
-
Office, business, and administrative buildings
-
Warehouse, logistics, and distribution complexes
-
Plants, factories, production facilities, and industrial enterprises
-
Elevators, grain storage facilities, and agro-industrial complexes
-
Hangars, large-span structures, and engineering facilities
Zaporizhzhia, Bazova Street
Operating fuel station complex
Restoration and strengthening of the base of a concrete slab and the foundation of a fuel dispenser at an operating fuel station complex
During the inspection of the roadway and the foundation of the fuel dispenser, local settlement of the concrete slab, the presence of voids beneath it, and loss of contact with the soil base were identified. Additionally, soil loosening was recorded in the foundation area of the dispenser, caused by prolonged transport loads, vibrations, and washout of fine soil particles, creating risks of further pavement deformation and reduced structural stability.
To restore full slab–soil contact, eliminate voids, increase the load-bearing capacity of the soil, and stabilize the foundation of the fuel dispenser without dismantling structures and without interrupting the operation of the fuel station, injection strengthening with a gel composite solution in two levels was applied.
Completed works:
During the execution of works, geodetic marking of drilling points was carried out in accordance with the design scheme, Ø45 mm boreholes were installed through the concrete slab and in the area of the fuel dispenser foundation, followed by staged injection of the gel composite solution at two levels with control of pressure and material consumption.
In the upper zone (−0.3…−1.2 m), injection was performed to fill voids under the concrete slab and restore slab–soil contact, while at depths up to −6.0 m, borehole injection compaction of loosened soil layers was carried out under pressure up to 8.0 MPa, ensuring the formation of a spatially compacted soil mass beneath the structures.
As a result, voids under the slab were eliminated, slab–soil contact was restored, deep compaction of weakened soil layers was achieved, and technological openings were sealed with restoration of the surface. The works were performed under continuous operation of the facility.
Result
As a result of the performed injection works, all voids beneath the concrete slab of the roadway were completely eliminated, and full contact with the soil base was restored. At the same time, deep compaction of loosened soil layers was carried out and the foundation base of the fuel dispenser was strengthened, ensuring the formation of a spatially stabilized soil mass beneath the structures.
The implemented measures made it possible to significantly increase the load-bearing capacity of the base, reduce the deformation characteristics of the soil, and eliminate the risks of further settlement and uneven pavement deformation. The operational stability of the concrete slab and equipment foundation was restored without dismantling structures, and all works were carried out under continuous operation of the fuel station complex.
Project duration: 15 calendar days
Kyiv, 2025–2026
METRO shopping center
Lifting and stabilization of a sunken industrial floor
During the technical inspection and geodetic survey at the shopping center, local and extended zones of settlement of the reinforced concrete floor slab were identified, with deviations reaching −50–60 mm from the design levels.
The investigation determined that the causes of deformation were unevenly compacted soil base during construction, as well as leaks from underground utilities during operation, which led to soil washout, additional compaction, and the formation of sub-slab voids with depths of 100–200 mm. The identified condition created a risk of loss of load-bearing capacity of the floor slab and further development of floor deformations, causing operational inconvenience.
Completed works:
To restore structural stability, deep injection of a gel composite solution was carried out to a depth of −2.0 m from the floor surface, according to a specially designed volumetric planning scheme.
To return the reinforced concrete floor to the design level and eliminate voids, gel composite injection was performed under pressure up to 8 MPa at a depth of −0.5 m from the floor surface.
All works were carried out without dismantling the existing floor covering and without interrupting the operation of the shopping center.
The total area of stabilization and restoration of the industrial floor level using the injection method amounted to 4,500 m².
Result
The reinforced concrete floor slab was restored to the design level, and the geometry of the surface was fully recovered across the entire injection area.
Stabilization of the slab and soil base was achieved, and further settlement was completely stopped.
The load-bearing capacity of the structure was restored, ensuring safe operation of the retail area.
Uniform load transfer from the floor slab to the stabilized soil base was ensured.
Project duration: 30 calendar days
OKKO fuel station, 2023
Fuel station
Restoration of the load-bearing capacity of the roadway slab and fuel dispenser foundations
During the operation of the fuel station, uneven settlement of fuel dispenser foundations and local deformations of the reinforced concrete roadway slab were recorded. Engineering investigations revealed the presence of voids beneath the slab up to 500 mm deep, formed as a result of soil washout due to damaged underground utilities and dynamic loads from traffic. The load-bearing capacity of the soil in the affected area was 0.7–1.0 kg/cm², which was insufficient to ensure stable performance of the structures.
To prevent further development of deformations, a decision was made to perform injection strengthening of the base with simultaneous filling of voids under the slab without interrupting the operation of the fuel station.
Completed works:
Geodetic marking of drilling points was carried out taking into account the location of underground utilities, and 47 injection boreholes Ø45 mm with a depth of up to 5.0 m were drilled. Staged injection of a gel composite solution was performed under controlled pressure up to 8 MPa, with monitoring of consumption and injection volumes at each borehole.
During the works, layer-by-layer filling of voids beneath the slab, compaction of loosened soil layers, and stabilization of fuel dispenser foundations were ensured. Throughout the injection process, geodetic and visual monitoring of slab position was carried out. After completion, packers were removed, and technological openings were sealed.
Result
As a result of the completed works, all voids beneath the roadway slab were completely eliminated, slab–soil contact was restored, and the load-bearing capacity of fuel dispenser foundations was increased.
Further settlement was stopped, the geometry of the roadway surface was stabilized, and long-term operational reliability of structures was ensured without excavation work and without interrupting the operation of the fuel station.
Project duration: 6 calendar days
Hamaliivka village, Kyivska Street, Lviv region, 2025
Grocery and non-food store
Gel composite stabilization of the soil base and lifting of the reinforced concrete floor slab to the design level
During the construction phase of the store, visual inspection revealed local settlement from the design level and the formation of cracks in the concrete floor slab.
Geodetic surveys identified unevenly compacted soil and a water-saturated base zone beneath the slab down to −4.0 m, which led to loss of load-bearing capacity and uneven slab deformation up to −65 mm from the design level.
This technical condition created hazardous operating conditions for the retail space.
Completed works:
To ensure stable operation, a technical solution was adopted with localized impact on the cause of deformations — specialized gel composite soil stabilization within the defined zone beneath the slab, without dismantling structures and without affecting the load-bearing elements of the building.
To fill voids and strengthen the base beneath the floor slab, gel composite injection was carried out to a depth of up to −4.0 m from the zero design floor level under pressure up to 8 MPa.
The total area of stabilization and restoration of the floor to the design level using the injection method amounted to 350 m².
Result
The reinforced concrete floor slab was lifted and restored to the design level, recovering the surface geometry across the entire injection area.
Stable performance of the slab together with the soil base was achieved — no further settlement is observed.
The load-bearing capacity of the structure was restored, ensuring reliable and safe operation of the retail space.
Uniform distribution and transfer of loads from the floor slab to the stabilized soil mass were ensured.
Project duration: 12 calendar days
Uman, Cherkasy region
Production and warehouse facilities of Umanpivo
Comprehensive strengthening of the foundation base of production buildings
During technical monitoring of the buildings, uneven settlement of foundations was identified in areas with heavy brewing equipment, along with the appearance of cracks in load-bearing walls and floor slabs, local reduction in soil density, and uneven floors in warehouse areas.
The main causes were determined to be long-term operation of the buildings, significant static and vibration loads from technological equipment, periodic soil moisture, and seasonal temperature fluctuations. To prevent further development of deformations and stabilize the structures, it was decided to perform injection strengthening of the soil base of foundations without stopping the production process.
Completed works:
To stabilize the foundation base, borehole injection technology by Inject was applied using injection solutions that ensure soil compaction and structural reinforcement of the soil mass. As part of the works, geodetic marking of strengthening zones and drilling of Ø45 mm boreholes up to 8.0 m deep were carried out in a staggered pattern in the most loaded areas of foundations and floor slabs.
Through the boreholes, staged injection of the solution under controlled pressure up to 8.0 MPa was performed, ensuring elimination of voids, compaction of loosened soil layers, and formation of overlapping reinforcement zones beneath the foundations.
After completion of the injection works, technological openings were sealed, a control geodetic survey was carried out, and all works were performed without dismantling equipment and without stopping production.
Result
As a result of the completed works, the load-bearing capacity of the soil base of foundations was increased, and deformation processes in the building structures were stabilized.
Further settlement was stopped, the level of floor slabs in warehouse areas was restored, and structural stability was ensured in zones with constant vibration and static loads.
All works were carried out without interrupting the production process, which made it possible to avoid downtime and ensure long-term safe operation of the production facilities.
Project duration: 16 working days
Kyiv, Fedorova Street, 2025
Retail premises
Injection works to eliminate moisture in basement walls
During rainy conditions, a visual inspection of the basement level revealed local areas of wall moisture penetration. The moisture appeared as wet spots on the masonry surface, darkening of the finishing layer, and increased moisture content of wall materials in the lower part of the premises. The affected zones had clear localization and were concentrated near structural joints and areas of potential leakage points.
The nature of the defect during rainy periods indicates penetration of atmospheric and groundwater moisture through the enclosing structures due to the capillary-porous structure of materials, as well as through existing microcracks and discontinuities.
Completed works:
To eliminate the causes of wall moisture penetration in the basement, a complex of injection waterproofing measures was carried out.
Gel composite injection was performed into the thickness of the masonry with extension beyond its boundaries to form a waterproof barrier in the adjacent soil mass. The waterproofing composition was injected under controlled pressure up to 8 MPa in areas of intensive moisture penetration.
After completion of the injection works, packers were removed, and the integrity of the masonry was restored by filling the holes with a specialized repair compound.
The works were performed without opening the structures, with minimal local intervention in the finishing layers at the injection points.
Result
Penetration of moisture through enclosing structures was stopped;
A waterproof zone was formed within the masonry and the adjacent soil mass;
Local areas of wall moisture in the basement were eliminated;
Conditions for further natural drying of structures were ensured;
Preconditions for the formation of efflorescence, finishing delamination, and biological damage were eliminated;
The operational characteristics of enclosing structures were restored.
Project duration: 2 days
Kyiv, Berezniakivska Street, 32
Educational Complex No. 209 “Suzirya”
Protection of the excavation pit against collapse and ensuring safe construction of a dual-purpose facility (radiation shelter)
During earthworks for the construction of an excavation pit with a depth exceeding −6.0 m, it became necessary to ensure its stability under conditions of sandy and sandy loam soils and dense urban development. The immediate proximity of an existing educational building and the significant excavation depth created increased risks of pit wall collapse, local soil slides, and possible deformations of adjacent structures.
To prevent these risks, a decision was made to perform injection soil stabilization along the perimeter of the excavation pit with the formation of a spatial protective soil mass acting as an injection-based retaining system.
Completed works:
To stabilize the pit walls, borehole injection technology by Inject was applied using a cement-silicate solution injected under pressure up to 8.0 MPa. As part of the works, geodetic marking of drilling points was carried out, followed by drilling 909 boreholes with a diameter of 45 mm to a depth of up to −8.0 m along the perimeter of the excavation pit.
Through the boreholes, controlled injection of calculated solution volumes was performed with monitoring of material consumption at each point. This ensured soil mass compaction and the formation of overlapping injection zones, creating a continuous reinforced contour that protects the excavation pit from collapse.
The works were carried out using compact equipment under the conditions of an operating educational facility without interrupting construction processes.
Result
As a result of the completed works, a spatially reinforced injection soil mass was formed along the perimeter of the excavation pit, providing reliable protection of its walls against collapse and local soil slides.
The stability of soils in the excavation zone was significantly increased, creating safe conditions for further construction works and eliminating risks of deformations of adjacent structures.
All works were performed without interrupting the operation of the educational facility and with minimal impact on the surrounding development.
Project duration: 15 working days
Kyiv, Dniprovskyi District, Suleimana Stalskoho Street, 12, 2024–2025
Secondary General Education School No. 158 (Grades I–III)
Strengthening of the foundation base of shelters and engineering preparation of the building for further arrangement of a civil protection facility (bomb shelter)
During the technical inspection of the basement premises of the school, intended for further conversion into a civil protection shelter, local settlement of the soil base of foundations, cracks in walls and partitions, and a decrease in soil density beneath certain foundation areas were identified.
The detected defects were caused by changes in hydrogeological conditions, the influence of groundwater, and natural soil settlement processes, creating risks of further structural deformations, local soil slides, and soil collapse in the foundation zone during operation and construction works.
To ensure safe operation of the building and create the necessary engineering conditions for the arrangement of a bomb shelter, a decision was made to perform injection strengthening of the soil base of foundations.
Completed works:
To stabilize the base, borehole injection technology by Inject was applied using a gel composite solution. In the basement premises, geodetic marking of injection zones was carried out, and approximately 400 injection boreholes with a diameter of 45 mm were drilled in two rows along the foundations to a depth of up to 2.0 m.
The injection was performed in stages with the introduction of calculated solution volumes under pressure up to 8.0 MPa, with continuous monitoring of material consumption and geodetic monitoring of structural condition.
During injection, overlapping zones were formed, which ensured compaction of loosened soil areas and the creation of a continuous reinforced mass beneath the foundations.
Result
As a result of the performed injection works, compaction and stabilization of the soil base of foundations were achieved, its load-bearing capacity was increased, and a spatially reinforced soil mass was formed, providing protection against further settlement, local deformations, and soil collapse in the foundation zone.
The completed works created a reliable engineering base for the further arrangement of a bomb shelter and ensured safe operation of civil protection structures without intervention in existing building structures.
Project duration: 12 calendar days
Kyiv, Verkhovynna Street, 2024
Oncology center — public medical institution
Strengthening of foundation bases
According to the results of the engineering and technical inspection of the facility, local settlement of the soil base of foundations, vertical and diagonal cracks in load-bearing walls and partitions, as well as signs of reduced soil density beneath certain foundation areas were identified.
The detected defects were accompanied by initial structural deformations and were caused by changes in hydrogeological conditions, uneven soil moisture, and natural settlement processes. To stabilize the building structures and restore the load-bearing capacity of the soil base, it was decided to carry out a complex of injection works without dismantling structures and without interrupting the operation of the medical institution.
Completed works:
To strengthen the foundation base, borehole injection technology by Inject was applied using a gel composite solution. As part of the works, geodetic marking of injection zones was carried out, and 478 injection boreholes with a diameter of 45 mm and a depth of up to 6.0 m were drilled in two rows along the inner and outer sides of the building.
Through the boreholes, staged injection of the solution under controlled pressure up to 8.0 MPa was performed with control of material consumption and real-time geodetic monitoring of settlement. During injection, overlapping compaction zones were formed, ensuring stabilization of loosened soil areas and the creation of a reinforced soil mass beneath the foundations.
After completion of the works, technological openings were sealed, and the work areas were restored to operational condition.
Result
As a result of the completed works, the load-bearing capacity of the soil base of foundations was restored, deformation processes were stabilized, and further settlement of structures was stopped.
The formed injection soil mass ensured uniform load distribution from the building, increased its spatial stability, and extended the period of safe operation of the structure.
All works were carried out without interrupting the operation of the medical institution and without affecting hospital activities.
Project duration: 14 working days
Kyiv
Preschool Educational Institution No. 395
Installation of a waterproofing barrier and partial base strengthening
The basis for the engineering and technical inspection was the recorded cases of groundwater penetration into the basement premises, where a civil protection shelter is located. This required an assessment of the condition of the soil base of foundations and the existing waterproofing system.
The inspection revealed increased soil moisture in the foundation zone, signs of capillary moisture penetration into building structures, local areas of soil loosening, and risks of further deformation development. The main causes were identified as a high groundwater level, partial loss of effectiveness of the existing waterproofing layer, and malfunction of the drainage system.
To prevent further moisture penetration and stabilize the soil base, a decision was made to perform injection installation of a waterproofing barrier combined with local foundation base strengthening.
Completed works:
To implement the technical solution, borehole injection technology by Inject was applied using a gel composite solution. Along part of the building perimeter, engineering and geodetic marking was carried out, and 319 boreholes up to 3.0 m deep were drilled.
Through the boreholes, gel composite injection was performed under controlled pressure up to 8.0 MPa, ensuring the formation of a waterproof injection barrier within the soil mass and simultaneous compaction of loosened foundation base areas.
After completion of the injection works, technological openings were sealed with repair compounds, and the work area was restored to operational condition. All works were carried out without dismantling structures and without interrupting the operation of the facility.
Result
As a result of the completed works, a continuous waterproofing barrier was formed, which blocks the penetration of groundwater moisture into the foundation structures and prevents further moisture ingress into basement premises, including the civil protection shelter.
At the same time, local strengthening of the soil base of the foundation was achieved, increasing its density and stability, which reduced the risks of further deformations and formation of cracks in building structures.
The implemented measures ensured long-term protection of foundations and increased the operational reliability of the facility without interfering with its operation.
Kyiv, Vyshhorodska Street, 2024
Bomb shelter at a medical facility
Strengthening and stabilization of the foundation base of a civil protection shelter
During the inspection of the technical condition of the civil protection shelter, which is part of the critical infrastructure of a medical facility, local settlement of the soil base of foundations, cracks in walls and slabs, as well as areas of soil loosening were identified, leading to reduced structural tightness.
The detected defects were caused by changes in hydrogeological conditions, increased soil moisture, insufficient efficiency of existing drainage solutions, and the long service life of the structure. Considering the status of the facility as a civil protection shelter and the requirement for continuous operational readiness, a decision was made to perform injection strengthening of the soil base of foundations with restoration of structural stability and tightness.
Completed works:
As part of the technical solution, borehole injection technology by Inject was applied, involving the introduction of injection solutions into the soil base for its compaction and stabilization. In problem areas, boreholes with a diameter of 45 mm and a depth of up to 8.0 m were drilled, followed by staged injection of the solution under controlled pressure up to 8.0 MPa.
During injection, voids were eliminated, and overlapping compaction zones were formed beneath the foundations, ensuring restoration of the stability of the soil mass.
After completion of the works, technological openings were sealed, and the structures were restored to operational condition without any dismantling works.
Result
The performed injection strengthening ensured an increase in the load-bearing capacity of the soil base of foundations, stabilization of structures, and elimination of the causes of further settlement.
The tightness of the civil protection shelter was improved, ensuring its reliable operation under emergency conditions without interrupting the functioning of the facility.
Project duration: 8 calendar days
Warranty period: 5 years
Kyiv, Yakutska Street, 2024
Non-residential building
Foundation strengthening and injection of masonry cracks
During the operation of the building constructed in the 1960s–1970s, uneven settlement of a building corner was recorded, accompanied by vertical and diagonal cracks in the masonry, local delamination of finishing layers, and loss of foundation–soil contact.
The inspection revealed loosened soil zones and voids in the foundation area, formed as a result of prolonged moisture exposure due to a malfunctioning drainage system. The identified defects created risks of further structural deformation and loss of load-bearing capacity.
Dismantling the structures and constructing new foundations was technically complex and economically impractical, therefore a complex of injection works was selected as the solution.
Completed works:
To stabilize the structures, strengthening of the soil base of the foundation was carried out using borehole injection of a gel composite solution.
Within the deformation zone, injection boreholes Ø45 mm with a depth of up to 3.0 m were drilled, followed by staged injection under controlled pressure, which ensured:
-
filling of voids in the foundation zone;
-
compaction of loosened soil layers;
-
restoration of foundation–soil contact;
-
formation of stabilizing injection masses.
At the same time, crack injection in masonry was performed: holes Ø18 mm were drilled along the cracks at 300 mm spacing, packers were installed, and gel composite injection was carried out under controlled pressure, followed by sealing and restoration of the masonry surface.
The total length of injected cracks amounted to approximately 75 linear meters.
Result
As a result of the completed works, the foundation base was stabilized and further development of deformations was completely stopped.
The masonry cracks were injected and sealed, restoring the structural integrity of the building corner.
Long-term structural stability was ensured without the need for large-scale dismantling works.
Project duration: 11 calendar days
Kotsiubynske urban-type settlement, Kyiv region
Sports equipment warehouse
Comprehensive stabilization of the floor slab and foundations of a 2,400 m² warehouse complex
During the operation of the warehouse building, local subsidence of the floor slab, formation of cracks in the lower part of the walls, and loss of floor levelness were recorded. The inspection revealed the presence of significant voids beneath the slab as well as local zones of soil base loosening under the foundations, caused by uneven soil compaction, moisture impact, and dynamic loads from storage and movement of heavy equipment.
Completed works:
To stabilize the structures, drilling of injection boreholes Ø 45 mm with a depth of up to 6.0 m was carried out within the floor slab and foundation zones. Through these boreholes, stage-by-stage controlled injection of a gel composite solution was performed under regulated pressure, with continuous monitoring of material consumption and structural condition.
During the injection process, voids beneath the slab were filled, loosened soil layers were compacted, and a stabilized soil mass was formed under the foundations.
The total cement consumption amounted to approximately 130 tons.
After completion of the injection works, the technological holes were sealed, with restoration of the floor surface.
Result
The voids beneath the floor slab were completely eliminated, the contact between the slab and the soil base was restored, and the foundation base of the building was stabilized.
The processes of further subsidence were stopped, the development of cracks in the walls was halted, and the operational levelness of the floor was restored without dismantling structures and without interrupting warehouse operations.
Project duration: 30 working days
Borodyanka, 2026 (reconstruction)
Inclusive Resource Center
Strengthening of the soil base of foundations and prevention of excavation wall collapse
During the technical inspection of the building, manifestations of uneven foundation performance were identified, expressed in cracks in foundation structures, cracks in load-bearing walls, and damage to the integrity of the blind area. The analysis of causes showed that the upper layers of the soil base had lost density due to natural settlement and washing out of fine particles, which led to a decrease in their bearing capacity.
As part of the reconstruction, the construction of an excavation for a shelter extension near the existing foundations was planned. Given the current soil condition, earthworks could have caused excavation wall collapse and additional deformation of the building. This determined the need for preliminary engineering stabilization of the soil mass by deep injection using Inject technology. Solving such engineering challenges is a core specialization of our company.
Completed works:
The works were carried out in accordance with the design scheme in two stages by installing bored injection holes Ø 45 mm with a depth of up to 4 m.
A special gel composite solution was used for injection. This approach ensures full spatial coverage of the injection zones and the formation of a continuous stabilized soil mass within the future excavation area.
Within the project, 72 boreholes were completed with a total drilling length of 288 linear meters. During the execution of the works, instrumental monitoring of the structural condition was carried out.
Result
After completion of the injection, a densified soil-cement mass was formed within the soil body, which ensured:
-
termination of further development of cracks and uneven settlements;
-
increased stability of the foundation base;
-
formation of an anti-collapse barrier in the area of the future excavation;
-
preservation of excavation wall stability during soil removal without the use of additional retaining structures;
-
creation of a reliable base for the construction of the shelter extension.
Project duration: 7 calendar days
Ruzhyn, Zhytomyr region, 2025–2026
Ruzhyn Gymnasium
Complex of works for strengthening the soil base of part of the foundations of Ruzhyn Gymnasium
During the inspection and geodetic survey of the Ruzhyn Gymnasium building, aimed at determining the degree of soil compaction and strengthening, characteristic signs of loss of bearing capacity of the soil base under part of the foundations were identified.
Local subsidence of the base, vertical and diagonal cracks in load-bearing walls with openings up to 40 mm, and loss of density of the foundation soil base were recorded. The causes included changes in hydrogeological conditions, drainage system malfunction, uneven soil moisture, and natural long-term settlement of the base.
The operational requirement was to perform the works without interrupting the educational process and without intervention in the building structures.
Completed works
To stabilize and strengthen the foundation base, as well as to create a waterproofing barrier, the Inject bored injection technology using a gel composite solution was applied.
Injection of the gel composite solution was carried out under pressure up to 8 MPa to a depth of up to 7 m, resulting in elimination of voids, reduction of soil porosity, and improvement of the strength and deformation characteristics of the soil.
The total number of boreholes amounted to 1081 units.
Result
The works were carried out without destruction and without the need for further restoration of existing structures, utilities, finishes, landscaping elements, or greenery of the adjacent territory, and without interrupting the educational process.
The soil base of the foundations was stabilized and strengthened, and the development of deformation processes was stopped. Geodetic monitoring during the execution ensured control over the building behavior throughout the injection process.
The achieved result fully complies with the requirements of the design documentation and technical specifications, and the provided warranty period confirms the reliability of the adopted engineering solution.
Project duration: 25 calendar days
Kutsivka village, Kirovohrad region, 2021
Elevator
Stabilization of the elevator roadway and elimination of sub-slab voids
During the operation of the elevator complex territory, local subsidence of the concrete roadway and formation of significant sub-slab voids were recorded. Engineering inspection revealed voids beneath the slabs with depths up to 1200 mm, caused by soil washout due to drainage system failure and prolonged dynamic loads from heavy transport.
Further operation without stabilization of the base could have led to progressive destruction of the pavement and loss of bearing capacity of the structures.
Completed works
To restore the bearing capacity of the base and stabilize the roadway, a complex of injection works was carried out:
• engineering marking of subsidence zones and voids was performed;
• technological openings Ø350 mm were arranged for sand flushing under the slabs to preliminarily fill large voids;
• sand flushing was carried out until complete filling of the sub-slab space and restoration of primary support;
• after stabilization of the sand base, drilling of injection boreholes Ø45 mm with a depth of up to 4.5 m was performed;
• stage-by-stage injection of a gel composite solution under regulated pressure was carried out for final filling of residual voids and compaction of the soil base;
• stabilizing injection masses were formed beneath the roadway slabs;
• control of elevation marks and sealing of technological and injection openings after completion of the works were performed.
The total number of injection boreholes amounted to 420 units.
The slab lifting range was 10–55 mm.
Result
• the voids beneath the roadway slabs were completely eliminated;
• uniform performance of the soil base was restored;
• the position of the concrete slabs was stabilized and their design elevations were restored;
• risks of further subsidence were eliminated without dismantling the pavement and without interrupting the operation of the enterprise;
• long-term operational reliability of the transport zones of the elevator complex was ensured.
Project duration: 21 working days
Kyiv region, Makariv district, Pashkivka village, Kirova Street 4, 2020
Pashkivka Secondary School of I–III Levels
Stabilization of school foundations
During the operation of the school building, cracks in load-bearing walls and interstory slabs, as well as local zones of foundation subsidence, were recorded. Engineering inspection revealed uneven compaction of the soil base and a decrease in its bearing capacity.
The main causes of deformation were prolonged exposure to atmospheric precipitation, malfunction of the drainage system, and damage to the foundation waterproofing, which led to soil over-saturation and the formation of weakened zones beneath the building foundations.
To restore structural stability, a decision was made to strengthen the foundation soil base using the method of gel composite injection with Inject technology.
Completed works
Engineering marking of foundation strengthening zones was carried out, and a layout of injection boreholes in a staggered pattern was developed to ensure uniform formation of a stabilization mass. Drilling of boreholes Ø45 mm with a depth of up to 4 m was performed, followed by installation of injection packers.
Through the packer system, stage-by-stage injection of a gel composite solution was carried out under controlled pressure up to 8 MPa, ensuring filling of voids, compaction of weakened soils, and formation of a stabilizing injection field beneath the foundations. A total of 294 injection boreholes were completed.
During the execution of the works, continuous geodetic monitoring of foundation stabilization and tracking of possible structural deformations were performed. The works were carried out on an operating educational facility with compliance to enhanced safety requirements and an agreed execution schedule.
Result
As a result of the performed injection works, the bearing capacity of the foundation soil base was restored and uniform performance of the building structures was ensured.
The development of cracks in walls and slabs was stopped, the prerequisites for further deformations were eliminated, and the overall operational reliability of the structure was improved.
Project duration: 22 working days
1st May Street 1a, Baryshivka, Kyiv region, 2017
Gas station
Strengthening of the soil base of the gas station territory by deep injection method
On the territory of the gas station, massive uneven subsidence of the soil base was recorded, which led to significant deformation of the pavement and deviation from design elevations up to 480 mm. As a result, the asphalt concrete roadway was destroyed, the blind area of the operator building was damaged, and zones with reduced bearing capacity of the base were formed.
Engineering investigations revealed the presence of loosened soils within the base thickness and the need for comprehensive deep stabilization of the entire area without dismantling existing structures. During the execution of the works, the gas station was completely shut down.
Completed works
To stabilize the territory, the technology of deep injection of a gel composite solution was applied, which allowed the formation of reinforced injection masses in weak soil layers.
Within the project, the following works were performed:
• geodetic layout of the injection field across the entire gas station territory;
• drilling of 1059 injection boreholes Ø45 mm;
• execution of vertical and inclined boreholes (up to 70°) for stabilization of zones under foundations and enclosing structures;
• injection of the gel composite solution to a depth of up to 10 m;
• strengthening of slopes around the territory using injection masses;
• stage-by-stage control of injection parameters and soil stabilization during the execution of the works.
After completion of the injection, preparation of the base and installation of a new concrete slab of the roadway were carried out.
Result
• the soil base across the entire gas station territory was fully stabilized;
• processes of further settlement and pavement deformation were stopped;
• the bearing capacity of the bases under foundations and roadway was increased;
• the possibility of restoring the roadway without the risk of repeated subsidence was ensured;
• a long-term stable base for further operation of the facility was created.
Project duration: 30 calendar days
Boryspil International Airport, 2021
Boiler house building
Strengthening of the foundation soil base of the boiler house by injection method
During the operation of the boiler house building, uneven settlement of foundations, deformation of wall structures, and local subsidence of floor slabs were recorded. Engineering and geotechnical investigations, including dynamic probing, revealed the presence of loosened and over-saturated soils within the active zone up to 5.0 m, as well as local voids and zones of loss of bearing capacity beneath the foundations.
The main causes of deformation were identified as soil saturation due to leakage of engineering networks and washing out of fine soil particles. Considering the status of the facility as critical infrastructure, a decision was made to perform injection strengthening of the soil base without interrupting the operation of the boiler house.
Completed works
Geodetic layout of the injection field was carried out, followed by drilling of injection boreholes Ø45 mm with a depth of up to 5.0 m within the deformation zones of foundations and floor slabs. A total of 196 boreholes equipped with injection packers were installed.
Through the packer system, stage-by-stage injection of a gel composite solution was performed under controlled pressure up to 8 MPa, with manometric monitoring of injection parameters.
During the works, voids were filled, loosened soil layers were compacted, and a spatial reinforced injection mass was formed beneath the boiler house foundations.
After completion of the injection, sealing of technological openings and control geodetic measurements of structural stability were carried out.
Result
The performed injection works ensured restoration of the design bearing capacity of the foundation soil base, termination of uneven settlement processes, and stabilization of floor slabs and wall structures of the building.
The formed injection mass improved the deformation characteristics of the base and ensured long-term operational reliability of the boiler house without interrupting its operation.
Project duration: 7 working days
Kyiv, Mezhyhirska Street 82B, 2020
Industrial building
Stabilization of the base of a concrete floor during the reconstruction of an industrial building
During the reconstruction of the industrial building, engineering inspection revealed local subsidence of the concrete floor, loss of density of the soil base, and formation of sub-slab voids at significant depth.
The identified defects created risks of further structural deformation and complicated the execution of planned construction and repair works. To ensure safe continuation of the reconstruction, it was decided to perform deep stabilization of the soil base using bored injection technology without dismantling the concrete slab.
Completed works
Marking of strengthening zones within the reconstructed premises was carried out, followed by drilling of injection boreholes Ø45 mm with a spacing of 1.0 m. The boreholes were installed to a depth of up to 6.0 m to stabilize weak soil layers.
Through a system of injection packers, layer-by-layer injection of a gel composite solution was performed under controlled pressure up to 8.0 MPa, with continuous geodetic monitoring of the concrete slab position.
After completion of the injection, sealing of technological openings and control measurements of base stability were carried out.
Result
As a result of the performed works, sub-slab voids were eliminated, the soil base was compacted to a depth of up to 6 m, and the design bearing capacity of the base under the concrete floor was restored.
The prerequisites for further settlement and structural deformations were eliminated, and a reliable base was created for the next stages of building reconstruction.
Project duration: 7 working days
Pochuiky village, Popilnia district, Zhytomyr region, 2020
Monsanto Seeds LLC
Stabilization of the storage pond embankment with restoration of slope geometry
During the operation of the storage pond on the territory of an industrial enterprise, deformation of part of the embankment and violation of slope geometry were recorded, caused by the development of landslide processes, erosion, and reduction in the density of the soil base.
In certain areas, local subsidence and washouts formed, creating a risk of further destruction of the slope, loss of its stability, and potential environmental hazards. To prevent further deformation, a decision was made to carry out a complex of injection works for stabilization of the soil mass and restoration of the design slope geometry.
Completed works
Engineering marking of stabilization zones was performed, followed by drilling of injection boreholes Ø45 mm with a depth of up to 9 m in a staggered pattern with a spacing of 0.5 m.
Through the boreholes, stage-by-stage injection of a gel composite solution was carried out under controlled pressure up to 8.0 MPa, ensuring compaction of loosened soil layers and formation of a stabilizing injection mass within the embankment zone.
Simultaneously, geodetic control of slope geometry was carried out, along with local restoration of its design shape using stabilized soil.
After completion of the injection, the boreholes were sealed, and the slope surface was restored to the design elevations.
Result
As a result of the performed works, the soil mass of the storage pond embankment was stabilized, the design slope geometry was restored, and the prerequisites for further landslide and erosion processes were eliminated.
The bearing capacity of the soil base was increased, ensuring long-term stability of the slope and safe operation of the hydraulic structure without interruption of the enterprise’s technological processes.
Project duration: 21 working days
Kyiv, Kyrylivska Street 58, 2016
Gas station
Strengthening of the soil base and lifting of floors
On the territory of the gas station, uneven settlement of floor structures was identified, caused by a decrease in the bearing capacity of the soil base and local zones of soil loosening. Further development of deformations created a risk of damage to pavement structures and engineering equipment. A key technological requirement was to ensure continuous operation of the gas station during the strengthening works.
Completed works
A complex of geotechnical strengthening works was carried out using the method of deep injection of a gel composite material. Through drilled injection boreholes with a depth of up to 9.0 m, layer-by-layer injection of the material was performed under controlled pressure, forming reinforced soil-cement masses and compacting the surrounding soils.
During the injection process, geodetic monitoring of structural movements was carried out, which made it possible to perform controlled lifting of the subsided floor sections to the design elevations without creating additional stresses in the structures.
The works were performed in stages, in localized sections, without interrupting the operational processes of the gas station.
Result
As a result of the performed works, the deformation modulus and bearing capacity of the soil base were increased, zones of loosening were eliminated, and settlement processes were stabilized.
Restoration of the design elevations of floor structures was achieved, ensuring uniform performance of the base under load.
Further monitoring confirmed the cessation of deformations, enabling the reconstruction of the facility and its safe further operation.
Project duration: 4 working days
Completed Projects
View other works and projects
Architectural Heritage
- Historic residential buildings
- Administrative buildings of historic development
- Palaces and estates
- Museums and exhibition spaces
- Religious and sacred structures
Private properties
- Private residential houses
- Cottages and townhouses
- Multi-family residential buildings
- Building extensions and renovated buildings
- Utility and auxiliary structures


