Quality Policy
EXPRESS INJECTION TECHNOLOGIES LLC
Version dated March 2, 2026
1. General Provisions
Limited Liability Company “EXPRESS INJECTION TECHNOLOGIES” (EDRPOU Code 40637037) operates in the field of injection technologies, strengthening and stabilization of foundations, lifting and leveling of concrete structures, anti-filtration protection, repair and reinforcement of building structures.
The Company recognizes a high level of responsibility when performing works on facilities of various consequence classes and implements a systematic approach to quality management.
2. Regulatory and International Framework
In its activities, the Company is guided by:
current DBN, DSTU, and technical regulations of Ukraine;
the Law of Ukraine “On Regulation of Urban Development Activities”;
industry-specific construction standards;
contractual requirements with clients.
The Company is guided by the principles of international standards:
ISO 9001 (quality management system);
ISO 14001 (environmental management);
ISO 45001 (occupational health and safety);
ISO 37001 (anti-corruption management).
In case of implementation of a certified management system, this is indicated separately.
3. Scope of Application
This Policy applies to:
execution of construction and installation works;
engineering calculations and technical solutions;
procurement of materials;
contractor management;
interaction with clients;
internal management processes.
4. Work on Facilities by Consequence Class
The Company performs works on facilities of the following consequence classes:
CC1 — minor consequences;
CC2 — medium consequences;
CC3 — significant consequences (within the limits of valid permits).
When performing works on CC2 and CC3 facilities, the following are ensured:
enhanced technical supervision;
documentation of production processes;
engineering support;
compliance with occupational safety requirements;
control of material compliance.
5. Quality Management Principles
The Company adheres to the following principles:
Process approach — each stage of work has defined inputs and outputs;
Risk management — analysis of technical risks before starting work;
Preventive approach — prevention of defects rather than their elimination;
Traceability — ability to track materials and technological solutions;
Management responsibility — control over the implementation of standards;
Continuous improvement.
6. Quality Assurance
To ensure consistent quality, the Company:
conducts technical inspections of facilities;
performs engineering calculations;
uses certified materials;
controls supplier quality;
maintains production documentation;
monitors work execution;
implements internal control measures.
7. Risk Management
Before the start of work, the following are assessed:
technical risks;
geological conditions;
impact on adjacent structures;
possible consequences for CC2/CC3 facilities.
The results of the analysis are taken into account when selecting the technology.
8. Environmental Responsibility
The Company strives to minimize environmental impact by:
rational use of materials;
waste control;
compliance with environmental legislation.
9. Occupational Health and Safety
The Company ensures:
compliance with occupational safety regulations;
conducting safety briefings;
use of personal protective equipment;
safety control on construction sites.
10. Interaction with Clients
The Company guarantees:
transparency in pricing;
technical justification of solutions;
compliance with contractual obligations;
provision of warranties in accordance with contracts.
11. Continuous Improvement
The Company regularly:
analyzes completed projects;
evaluates the effectiveness of technologies;
improves staff qualifications;
enhances internal procedures.
12. Management Responsibility
The Company’s management:
ensures the implementation of this Policy;
monitors compliance;
bears responsibility for the quality of performed works.
13. Final Provisions
The Quality Policy is an open document and is available for review by clients, partners, and regulatory authorities.
Effective date: March 2, 2026.